Project Resource Library
Table of Contents
EIS Addendum and Consistency Analysis - City of Renton
EIS Addendum and Consistency Analysis
EIS Addendum and Consistency Analysis
Final EIS
Note: Final EIS files were posted on March 1, 2018.
Note: Final EIS files were posted on March 1, 2018.
Final EIS Volumes
Note: These are large files and may take a moment to download.
Volume 1 - Energize Eastside Final EIS (Note: This contains the main body of the document.)
Volume 2 - Technical Appendices
Volume 3 - Phase 1 Draft EIS Comments and Responses
Volume 3 Attachments
Volume 4 - Phase 2 Draft EIS Comments and Responses
Volume 4 Attachments
Final EIS Individual Sections
Cover Page, Table of Contents, Fact Sheet
Chapter 1 - Introduction
Chapter 2 - Project Alternatives
Chapter 3 - Errata
Chapter 4 - Long Term Impacts and Mitigation Introduction
Chapter 4.1 - Land Use and Housing
Chapter 4.2 - Scenic Views and Aesthetics
Chapter 4.3 - Water Resources
Chapter 4.4 - Plants and Animals
Chapter 4.5 - Greenhouse Gases
Chapter 4.6 - Recreation
Chapter 4.7 - Historic and Cultural Resources
Chapter 4.8 - Electric and Magnetic Fields
Chapter 4.9 - Pipeline Safety
Chapter 4.10 - Economics
Chapter 4.11 - Earth Resources
Chapter 5 - Short-term Construction Impacts
Chapter 6 - Summary of Comments and Responses
Chapter 7 - Cumulative Impacts
Chapter 8 - Significant Unavoidable Adverse Impacts
Chapter 9 - References
Chapter 10 - Distribution List
Chapter 11 - Acronyms Glossary
Appendix A - Construction and Access
Appendix B - Land Use
Appendix C (Sections C-1 and C-2) - Views and Aesthetics
Appendix C (Section C-3) - Views and Aesthetics
Appendix D - Critical Areas Regulations
Appendix E - Plants and Animals
Appendix F - Recreation-related Policies
Appendix G - Historic Resources
Appendix H - EMF
Appendix I - Pipeline Safety
Appendix J (Section J-1) - Phase 1 Comments and Responses
Appendix J (Section J-2) - Phase 1 Comments and Responses
Appendix K - Phase 2 Comments and Responses
Appendix L - Data Sources
Appendix M - Mitigation
Interactive Maps
You can access interactive maps that show water resources, parks and recreation facilities and trees potentially impacted by PSE’s Proposed Alignment, as well as existing and proposed pole locations, by clicking on the links provided below. The first two maps are similar to the maps included in the Final EIS, Section 4.3.5 (Water Resources) and Section 4.6.5 (Recreation). The three maps give you the ability to zoom in to locations along the project corridor and to select key features. Use your mouse to click on a segment or recreation facility to bring up a pop-up window that provides additional information.
Water Resources Interactive Map
Recreation Interactive Map
Pole and Tree Locations Interactive Map
KMZ Files for Pole and Tree Locations
In addition to the interactive map for pole and tree locations, you can also download the kmz files for the pole and tree locations and view them in Google Earth on your computer.
Note: These are large files and may take a moment to download.
Volume 1 - Energize Eastside Final EIS (Note: This contains the main body of the document.)
Volume 2 - Technical Appendices
Volume 3 - Phase 1 Draft EIS Comments and Responses
Volume 3 Attachments
Volume 4 - Phase 2 Draft EIS Comments and Responses
Volume 4 Attachments
Final EIS Individual Sections
Cover Page, Table of Contents, Fact Sheet
Chapter 1 - Introduction
Chapter 2 - Project Alternatives
Chapter 3 - Errata
Chapter 4 - Long Term Impacts and Mitigation Introduction
Chapter 4.1 - Land Use and Housing
Chapter 4.2 - Scenic Views and Aesthetics
Chapter 4.3 - Water Resources
Chapter 4.4 - Plants and Animals
Chapter 4.5 - Greenhouse Gases
Chapter 4.6 - Recreation
Chapter 4.7 - Historic and Cultural Resources
Chapter 4.8 - Electric and Magnetic Fields
Chapter 4.9 - Pipeline Safety
Chapter 4.10 - Economics
Chapter 4.11 - Earth Resources
Chapter 5 - Short-term Construction Impacts
Chapter 6 - Summary of Comments and Responses
Chapter 7 - Cumulative Impacts
Chapter 8 - Significant Unavoidable Adverse Impacts
Chapter 9 - References
Chapter 10 - Distribution List
Chapter 11 - Acronyms Glossary
Appendix A - Construction and Access
Appendix B - Land Use
Appendix C (Sections C-1 and C-2) - Views and Aesthetics
Appendix C (Section C-3) - Views and Aesthetics
Appendix D - Critical Areas Regulations
Appendix E - Plants and Animals
Appendix F - Recreation-related Policies
Appendix G - Historic Resources
Appendix H - EMF
Appendix I - Pipeline Safety
Appendix J (Section J-1) - Phase 1 Comments and Responses
Appendix J (Section J-2) - Phase 1 Comments and Responses
Appendix K - Phase 2 Comments and Responses
Appendix L - Data Sources
Appendix M - Mitigation
Interactive Maps
You can access interactive maps that show water resources, parks and recreation facilities and trees potentially impacted by PSE’s Proposed Alignment, as well as existing and proposed pole locations, by clicking on the links provided below. The first two maps are similar to the maps included in the Final EIS, Section 4.3.5 (Water Resources) and Section 4.6.5 (Recreation). The three maps give you the ability to zoom in to locations along the project corridor and to select key features. Use your mouse to click on a segment or recreation facility to bring up a pop-up window that provides additional information.
Water Resources Interactive Map
Recreation Interactive Map
Pole and Tree Locations Interactive Map
KMZ Files for Pole and Tree Locations
In addition to the interactive map for pole and tree locations, you can also download the kmz files for the pole and tree locations and view them in Google Earth on your computer.

FEIS_Proposed_Poles.kmz | |
File Size: | 8 kb |
File Type: | kmz |

Feis_Tree_Survey.kmz | |
File Size: | 557 kb |
File Type: | kmz |

FEIS_Metadata_Surveyed_Trees.pdf | |
File Size: | 165 kb |
File Type: |
Permit Information Referenced in the Final EIS
Bellevue
(Note: Visit the City's website to see PSE's entire permit submittal for Bellevue. The files here only include those referenced in the Final EIS.)
(Note: The Bellevue permit package only covers the Lakeside substation portion of the Bellevue Central Segment, Richards Creek substation, and the Bellevue South Segment.)
Alternative Siting Analysis
Application for Land Use Approval - Conditional Use Permit
Application for Land Use Approval - Critical Land Use Permit
Bill to Form
Conditional Use Permit Proposal Description
Critical Areas Report
Critical Areas Delineation Report
Critical Areas Geologic Hazard Evaluation
Richards Creek Substation Plan Sheets
Richards Creek Substation Delineation Report
Richards Creek Substation Lighting Plan
Reliability Certification
Site Plan for Transmission Line
Vegetation Management Plan
Newcastle
(Note: Visit the City's website to see PSE's entire permit submittal for Newcastle. The files here only include those referenced in the Final EIS.)
Conditional Use Permit Application
Critical Area Review Application
Critical Areas Report
Critical Areas Report Addendum
Environmental Checklist
Land Surveyor's Certification
Significant Tree Inventory (C-2) No Variance
Significant Tree Inventory (C-16) Variance
Site Plan for Transmission Line (C-2) No Variance
Site Plan for Transmission Line (C-16) Variance
Variance Application
Assessor Maps
NE 28-24-05
NE 33-24-05
SE 28-24-05
SE 33-24-05
Easements
List of Newcastle Easements
Newcastle Easements
Talbot-Lakeside Rights Review
Washington State Superior Court Case No. 220056
Landscape Tiles
Newcastle Landscape Tiles
Sample Landscape Typical
Photo Simulations
KOP South 19 C-2 Corten No Variance
KOP South 20 C-2 Corten No Variance
KOP South 20 C-2 Green Pole No Variance
KOP South 21 C-2 Corten No Variance
KOP South 25 C-2 Corten No Variance
KOP South 25 C-2 Galvanized No Variance
KOP South 26 C-2 Corten No Variance
KOP South 26 C-2 Galvanized No Variance
KOP South 27 C-2 Corten No Variance
KOP South 19 C-16 Corten Variance
KOP South 19 C-16 Green Pole Variance
KOP South 20 C-16 Corten Variance
KOP South 20 C-16 Green Pole Variance
KOP South 21 C-16 Corten Variance
KOP South 21 C-16 Green Pole Variance
KOP South 25 C-16 Corten Variance
KOP South 25 C-16 Galvanized Variance
KOP South 25 C-16 Green Pole Variance
KOP South 26 C-16 Corten Variance
KOP South 26 C-16 Galvanized Variance
KOP South 27 C-16 Green Pole Variance
KOP South 27 C-16 Corten Variance
Bellevue
(Note: Visit the City's website to see PSE's entire permit submittal for Bellevue. The files here only include those referenced in the Final EIS.)
(Note: The Bellevue permit package only covers the Lakeside substation portion of the Bellevue Central Segment, Richards Creek substation, and the Bellevue South Segment.)
Alternative Siting Analysis
Application for Land Use Approval - Conditional Use Permit
Application for Land Use Approval - Critical Land Use Permit
Bill to Form
Conditional Use Permit Proposal Description
Critical Areas Report
Critical Areas Delineation Report
Critical Areas Geologic Hazard Evaluation
Richards Creek Substation Plan Sheets
Richards Creek Substation Delineation Report
Richards Creek Substation Lighting Plan
Reliability Certification
Site Plan for Transmission Line
Vegetation Management Plan
Newcastle
(Note: Visit the City's website to see PSE's entire permit submittal for Newcastle. The files here only include those referenced in the Final EIS.)
Conditional Use Permit Application
Critical Area Review Application
Critical Areas Report
Critical Areas Report Addendum
Environmental Checklist
Land Surveyor's Certification
Significant Tree Inventory (C-2) No Variance
Significant Tree Inventory (C-16) Variance
Site Plan for Transmission Line (C-2) No Variance
Site Plan for Transmission Line (C-16) Variance
Variance Application
Assessor Maps
NE 28-24-05
NE 33-24-05
SE 28-24-05
SE 33-24-05
Easements
List of Newcastle Easements
Newcastle Easements
Talbot-Lakeside Rights Review
Washington State Superior Court Case No. 220056
Landscape Tiles
Newcastle Landscape Tiles
Sample Landscape Typical
Photo Simulations
KOP South 19 C-2 Corten No Variance
KOP South 20 C-2 Corten No Variance
KOP South 20 C-2 Green Pole No Variance
KOP South 21 C-2 Corten No Variance
KOP South 25 C-2 Corten No Variance
KOP South 25 C-2 Galvanized No Variance
KOP South 26 C-2 Corten No Variance
KOP South 26 C-2 Galvanized No Variance
KOP South 27 C-2 Corten No Variance
KOP South 19 C-16 Corten Variance
KOP South 19 C-16 Green Pole Variance
KOP South 20 C-16 Corten Variance
KOP South 20 C-16 Green Pole Variance
KOP South 21 C-16 Corten Variance
KOP South 21 C-16 Green Pole Variance
KOP South 25 C-16 Corten Variance
KOP South 25 C-16 Galvanized Variance
KOP South 25 C-16 Green Pole Variance
KOP South 26 C-16 Corten Variance
KOP South 26 C-16 Galvanized Variance
KOP South 27 C-16 Green Pole Variance
KOP South 27 C-16 Corten Variance
 
Phase 2 Materials
 
Phase 2 Draft EIS
Phase 2 Draft EIS Comment Record
Note: This record includes emails, letters, meeting testimony and website comments received during the Phase 2 Draft EIS comment period. Due to its large size, it has been provided in three parts. They may take a few moments to download. To navigate the record and find a specific comment, we recommend downloading the files and using the bookmarks menus.
Part 1 - Phase 2 Draft EIS Comment Record, Emails and Letters
Part 2 - Phase 2 Draft EIS Comment Record, Public Hearing Testimony
Part 3 - Phase 2 Draft EIS Comment Record, Website Comment Form Entries
Phase 2 Draft EIS Public Hearings Summary
Hearings Summary
Consolidated Phase 2 Draft EIS and Appendices Files
Note: These are large files and may take a moment to download.
Energize Eastside Phase 2 Draft EIS Volume 1 - Draft EIS
Energize Eastside Phase 2 Draft EIS Volume 2 - Appendices
Individual Phase 2 Draft EIS Files
Cover, Table of Contents, Fact Sheet
Chapter 1 Introduction and Summary
Chapter 2 Project Alternatives
Chapter 3 Long-term (Operation) Impacts and Potential Mitigation (Note: Individual sections of Chapter 3 are provided below.)
Chapter 5 Cumulative Impacts
Chapter 6 Significant Unavoidable Adverse Impacts
Chapter 7 Errata
Chapter 8 References (Note: Please contact info@EnergizeEastsideEIS.org if you are unable to access sources cited in the Phase 2 Draft EIS.)
Chapter 9 Distribution List
Chapter 10 Acronyms and Glossary
Appendix A General Construction and Access Description
Appendix B Supplemental Information: Land Use
Appendix C Scenic Views and Aesthetic Environment Methodology
Appendix E PSE Vegetation Management Standards
Appendix F Recreation Policies
Appendix G Supplemental Information: Historic Resources
Appendix H Supplemental Information: EMF (Unique Uses in the Study Area)
Appendix I Supplemental Information: Pipeline Safety
Interactive Maps
You can access interactive maps that show water resources, parks and recreation facilities and trees potentially impacted by the action alternatives, as well as existing and proposed pole locations, by clicking on the links provided below. The first two maps are similar to the maps included in the Phase 2 Draft EIS, Section 3.3.5 (Water Resources) and Section 3.6.5 (Recreation). The three maps give you the ability to zoom in to locations along the project corridor and to select key features. Use your mouse to click on a segment or recreation facility to bring up a pop-up window that provides additional information.
Water Resources Interactive Map
Recreation Interactive Map
Pole and Tree Locations Interactive Map
KMZ Files for Pole and Tree Locations
In addition to the interactive map for pole and tree locations, you can also download the kmz files for the pole and tree locations and view them in Google Earth on your computer.
Phase 2 Draft EIS Comment Record
Note: This record includes emails, letters, meeting testimony and website comments received during the Phase 2 Draft EIS comment period. Due to its large size, it has been provided in three parts. They may take a few moments to download. To navigate the record and find a specific comment, we recommend downloading the files and using the bookmarks menus.
Part 1 - Phase 2 Draft EIS Comment Record, Emails and Letters
Part 2 - Phase 2 Draft EIS Comment Record, Public Hearing Testimony
Part 3 - Phase 2 Draft EIS Comment Record, Website Comment Form Entries
Phase 2 Draft EIS Public Hearings Summary
Hearings Summary
Consolidated Phase 2 Draft EIS and Appendices Files
Note: These are large files and may take a moment to download.
Energize Eastside Phase 2 Draft EIS Volume 1 - Draft EIS
Energize Eastside Phase 2 Draft EIS Volume 2 - Appendices
Individual Phase 2 Draft EIS Files
Cover, Table of Contents, Fact Sheet
Chapter 1 Introduction and Summary
Chapter 2 Project Alternatives
Chapter 3 Long-term (Operation) Impacts and Potential Mitigation (Note: Individual sections of Chapter 3 are provided below.)
- Section 3.1 Land Use and Housing
- Section 3.2 Scenic Views and the Aesthetic Environment
- Section 3.3 Water Resources
- Section 3.4 Plants and Animals
- Section 3.5 Greenhouse Gases
- Section 3.6 Recreation
- Section 3.7 Historic and Cultural Resources
- Section 3.8 Environmental Health – Electric and Magnetic Fields
- Section 3.9 Environmental Health – Pipeline Safety
- Section 3.10 Economics
Chapter 5 Cumulative Impacts
Chapter 6 Significant Unavoidable Adverse Impacts
Chapter 7 Errata
Chapter 8 References (Note: Please contact info@EnergizeEastsideEIS.org if you are unable to access sources cited in the Phase 2 Draft EIS.)
Chapter 9 Distribution List
Chapter 10 Acronyms and Glossary
Appendix A General Construction and Access Description
Appendix B Supplemental Information: Land Use
Appendix C Scenic Views and Aesthetic Environment Methodology
- Appendix C Attachment 1 – Diameter of Existing and Proposed Wire
- Appendix C Attachment 2 – Methodology and Visual Simulations (Note: This is a large file and may take a moment to download.)
Appendix E PSE Vegetation Management Standards
Appendix F Recreation Policies
Appendix G Supplemental Information: Historic Resources
Appendix H Supplemental Information: EMF (Unique Uses in the Study Area)
Appendix I Supplemental Information: Pipeline Safety
Interactive Maps
You can access interactive maps that show water resources, parks and recreation facilities and trees potentially impacted by the action alternatives, as well as existing and proposed pole locations, by clicking on the links provided below. The first two maps are similar to the maps included in the Phase 2 Draft EIS, Section 3.3.5 (Water Resources) and Section 3.6.5 (Recreation). The three maps give you the ability to zoom in to locations along the project corridor and to select key features. Use your mouse to click on a segment or recreation facility to bring up a pop-up window that provides additional information.
Water Resources Interactive Map
Recreation Interactive Map
Pole and Tree Locations Interactive Map
KMZ Files for Pole and Tree Locations
In addition to the interactive map for pole and tree locations, you can also download the kmz files for the pole and tree locations and view them in Google Earth on your computer.

Poles.kmz | |
File Size: | 15 kb |
File Type: | kmz |

Surveyed_Trees.kmz | |
File Size: | 882 kb |
File Type: | kmz |

Metadata_Surveyed_Trees.pdf | |
File Size: | 153 kb |
File Type: |
Meeting Materials
The following materials were available for review during the public hearings for the Phase 2 Draft EIS.
Exhibits
Permitting Handout - Updated March 2018
Notice of Phase 2 Draft EIS and Public Hearings
The following materials were available for review during the public hearings for the Phase 2 Draft EIS.
Exhibits
Permitting Handout - Updated March 2018
Notice of Phase 2 Draft EIS and Public Hearings
 
Scoping Documents
Scope of Analysis for Phase 2 Draft EIS
Phase 2 Draft EIS - Scope of Analysis Report
Note: This report summarizes the alternatives and the elements of the environment that are being evaluated in the Phase 2 Draft EIS.
Reopened Phase 2 Scoping Period, June 30 - August 1, 2016
Comment Summary Report
Comment Record
Scoping Notice
PSE Bypass Alternatives
Note: This letter provides information about the two new alternatives proposed by PSE during scoping
PSE Scoping Letter Regarding Bypass Routes
Original Phase 2 Scoping Period, April 14 - May 31, 2016
Comment Summary Report
Comment Record
Note: This record includes a copy of all comments received, including written comments submitted via emails, letters, comment cards, the online comment form, and oral testimony at public meetings. This is a large file and may take a few moments to download. To navigate the record and find a specific comment, we recommend downloading the file and using the bookmarks menu.
Public Scoping Meetings Summary
Scoping Notice
Scoping Meeting Exhibits
Scope of Analysis for Phase 2 Draft EIS
Phase 2 Draft EIS - Scope of Analysis Report
Note: This report summarizes the alternatives and the elements of the environment that are being evaluated in the Phase 2 Draft EIS.
Reopened Phase 2 Scoping Period, June 30 - August 1, 2016
Comment Summary Report
Comment Record
Scoping Notice
PSE Bypass Alternatives
Note: This letter provides information about the two new alternatives proposed by PSE during scoping
PSE Scoping Letter Regarding Bypass Routes
Original Phase 2 Scoping Period, April 14 - May 31, 2016
Comment Summary Report
Comment Record
Note: This record includes a copy of all comments received, including written comments submitted via emails, letters, comment cards, the online comment form, and oral testimony at public meetings. This is a large file and may take a few moments to download. To navigate the record and find a specific comment, we recommend downloading the file and using the bookmarks menu.
Public Scoping Meetings Summary
Scoping Notice
Scoping Meeting Exhibits
 
EIS Consultant Team Background Documents
FCS Group Economic Considerations Supplemental Analysis (Revised) - January 2017
Enertech Peer Review of EMF Report - January 2017
Enertech Peer Review of EMF Report - March 2017
Stantec Peer Review of Corrosion Report - May 2017
FCS Group Economic Considerations Supplemental Analysis (Revised) - January 2017
Enertech Peer Review of EMF Report - January 2017
Enertech Peer Review of EMF Report - March 2017
Stantec Peer Review of Corrosion Report - May 2017
 
Additional Background Documents
NACE Corrosion Paper No. 4389 - March 2014
Letter from Seattle City Light to City of Bellevue - June 2014
Letter from Olympic Pipe Line Company to City of Newcastle - July 2016
Letter from Seattle Public Utilities to City of Newcastle - August 2016
NACE Corrosion Paper No. 4389 - March 2014
Letter from Seattle City Light to City of Bellevue - June 2014
Letter from Olympic Pipe Line Company to City of Newcastle - July 2016
Letter from Seattle Public Utilities to City of Newcastle - August 2016
 
PSE Background Documents
PSE Alternative 1 Background Documents
Note: Information about the alternatives proposed during the original Phase 2 Scoping period
PSE Energize Eastside Proposal and Objectives Narrative - Phase 2
Route Options Maps
Span Length & Pole Height
Pole Types
Pole Finish
Corridor Pole Configuration Examples
PSE Energize Eastside Community Outreach Summary - April 2016
Other PSE Alternatives Background Documents
Reference Maps
Proposed Transmission Line Segment Options Map
Corrosion Report
Letter to PSE from Olympic Pipeline Company Regarding Corrosion Report - December 2016
DNV-GL Corrosion Report - December 2016
DNV-GL No Action Alternative AC Interaction Graphs - April 2017
DNV-GL No Action Alternative AC Interaction Summary - April 2017
EMF Report
Power Engineers EMF Report Addendum - March, 2017
Power Engineers EMF Report, Revised - March, 2017
Photo Simulations
Views and Visual Index Map
Visual Simulations
Note: This is a large file and may take a few moments to download.
Photo Simulation North 3 - July 2017
Photo Simulation North 3 - March 2016
Photo Simulation North 14 - Corten - August 2017
Photo Simulation North 14 - Galvanized - August 2017
Photo Simulation North 14 - March 2016
Photo Simulation North 15 - August 2017
Photo Simulation North 16 - August 2017
Photo Simulation Segment J (South 24) - April 2016
Photo Simulation Segment J (South 25) - April 2016
Photo Simulation Segment J (Central 18) - May 2014
Photo Simulation Segment P (South 26) - April 2016
Photo Simulation Segment P (South 27) - April 2016
Photo Simulation Central 3 - July 2017
Photo Simulation Central 3 - May 2016
Photo Simulation Central 4 - August 2017
Photo Simulation Central 4 - May 2016
Photo Simulation Central 5 - September 2017
Photo Simulation Central 5 - August 2017
Photo Simulation Central 5 - May 2016
Photo Simulation Central 13 - August 2016
Photo Simulation Central 15 - Corten - July 2017
Photo Simulation Central 15 - Galvanized - July 2017
Photo Simulation Central 15 - May 2016
Photo Simulation Central 18 - Corten - July 2017
Photo Simulation Central 18 - Galvanized - July 2017
Photo Simulation Central 20 - August 2017
Photo Simulation Central 20 - May 2016
Photo Simulation Central 21 - August 2017
Photo Simulation Central 21 - May 2016
Photo Simulation Central 22 - August 2017
Photo Simulation Central 22 - May 2016
Photo Simulation Central 23 - August 2016
Photo Simulation Central 24 - August 2016
Photo Simulation Central 25 - August 2016
Photo Simulation Central 26 - August 2016
Photo Simulation Central 27 - August 2016
Photo Simulation Central 28 - August 2017
Photo Simulation Central 28 - August 2016
Photo Simulation Central 29 - September 2016
Photo Simulation Central 30 - Corten - July 2017
Photo Simulation Central 30 - Galvanized - July 2017
Photo Simulation Central 30 - September 2016
Photo Simulation Central 30 Willow 1 Segment 2- November 2016
Photo Simulation Central 31 - August 2017
Photo Simulation Central 31 - November 2016
Updated Photo Simulation Central 32 - September 2016
Photo Simulation Central 33 - October 2016
Photo Simulation Central 34 - October 2016
Photo Simulation Central 35 - October 2016
Photo Simulation Central 36 - November 2016
Photo Simulation Central 37 - August 2017
Photo Simulation Central 38 - August 2017
Photo Simulation Central 38 - January 2017
Photo Simulation Central 39 - August 2017
Photo Simulation Central 40 - August 2017
Photo Simulation South 12 - August 2017
Photo Simulation South 12 - July 2017
Photo Simulation South 12 - March 2016
Photo Simulation South 19 (C2AB) - July 2017
Photo Simulation South 19 (C16) - July 2017
Photo Simulation South 19 - Updated January 2017
Photo Simulation South 20 (C2) - July 2017
Photo Simulation South 20 (C16) - July 2017
Photo Simulation South 20 - Updated January 2017
Photo Simulation South 21 (C2) - July 2017
Photo Simulation South 21 (C16) - July 2017
Photo Simulation South 21 - Updated January 2017
Photo Simulation South 23 - Corten - July 2017
Photo Simulation South 23 - Galvanized - July 2017
Photo Simulation South 23 - August 2016
Photo Simulation South 24 (G) - Galvanized - July 2017
Photo Simulation South 24 - with Cell Equipment - November 2017
Photo Simulation South 24 - July 2017
Photo Simulation South 24 W (C1) - July 2017
Photo Simulation South 24 W - September 2016
Photo Simulation South 25 (C2AB) - Galvanized - July 2017
Photo Simulation South 25 (C2AB) - July 2017
Photo Simulation South 25 (C1) - July 2017
Photo Simulation South 25 (C16) - Corten - July 2017
Photo Simulation South 25 (C16) - Galvanized- July 2017
Photo Simulation South 25 - Updated September 2016
Photo Simulation South 26 (C2) - Corten - July 2017
Photo Simulation South 26 (C2) - Galvanized - July 2017
Photo Simulation South 26 (C16) - Corten - July 2017
Photo Simulation South 26 (C16) - Galvanized - July 2017
Photo Simulation South 26 - January 2017
Photo Simulation South 27 (C2) - July 2017
Photo Simulation South 27 (C16) - July 2017
Photo Simulation South 27 - January 2017
Photo Simulation South 28 - April 2016
Photo Simulation South 29 - April 2016
Photo Simulation South 30 - April 2016
Photo Simulation South 31 - April 2016
Photo Simulation South 34 - June 2016
Photo Simulation Richards Creek Substation - August 2017
Photo Simulation Richards Creek Substation - January 2017
Cultural Resource Reports
Cultural Alternatives Analysis - Redacted Version - June 2016
Geotechnical Reports
Energize Eastside Project Revised Targeted Critical Areas Geologic Hazard Evaluation - Newcastle
Energize Eastside Project Revised Targeted Critical Areas Geologic Hazard Evaluation - Bellevue
Energize Eastside Project Revised Targeted Critical Areas Geologic Hazard Evaluation - Renton
Energize Eastside Project Geologic Hazards Evaluation and Preliminary Geotechnical Engineering Services Report - December 2014
Energize Eastside Project Phase II Geotechnical Engineering Services Report - June 6, 2016
Energize Eastside Project Geotechnical Engineering Services Report - June 8, 2016
Critical Area Reports
Bellevue Energize Eastside Project Critical Areas Delineation Report - May 2016
Bypass Routes 1 & 2 Energize Eastside Critical Areas Addendum - July 2016
King County Energize Eastside Project Critical Areas Delineation Report - May 2016
Newcastle Energize Eastside Project Critical Areas Delineation Report - May 2016
Redmond Energize Eastside Project Critical Areas Delineation Report - May 2016
Renton Energize Eastside Project Critical Areas Delineation Report - May 2016
Segment O Critical Areas Addendum - April 2016
Segment P Critical Areas Addendum - May 2016
Vegetation Impact Analysis
Existing Corridor Vegetation Management Image - August 2016
PSE Veg Impact Analysis Summary Updated - September 2016
PSE Veg Impact Analysis Summary Richards Creek Updated - September 2016
PSE Vegetation Management Standards, 230kv Transmission Lines Updated - September 2016
Tree Inventory Reports
Bellevue Energize Eastside Project Tree Inventory Report - May 2016
Bypass Routes 1 & 2 Energize Eastside Project Tree Inventory Report - July 2016
King County Energize Eastside Project Tree Inventory Report - May 2016
Newcastle Energize Eastside Project Tree Inventory Report - May 2016
Redmond Energize Eastside Project Tree Inventory Report - May 2016
Renton Energize Eastside Project Tree Inventory Report - May 2016
Richards Creek Parcel Tree Inventory Report - July 2016
Segment O Energize Eastside Project Tree Inventory Report - May 2016
Segment P Energize Eastside Project Tree Inventory Report - May 2016
Methodology for Vegetation Impact Analysis
Substation
Richards Creek Substation Draft Grading and Fencing Plan - August 2016
Richards Creek Substation 230kv Preliminary Development Plan - March 2015
Richards Creek Substation Preliminary Grading and Fencing Plan - June 2016
Other Documents
Telecommunication Facilities Diagram
Energize Eastside Pole Structure Types - August 2017
Energize Eastside Roadway Alignment Transmission Configurations and Easement Requirements, 230kv Transmission Lines - June 2016
Energize Eastside Photo Simulation Methodology - June 2016
General Construction and Access Description - August 2016
Olympic Pipe Line Company Construction and Right of Way Requirements - March 2016
PSE Alternative 1 Background Documents
Note: Information about the alternatives proposed during the original Phase 2 Scoping period
PSE Energize Eastside Proposal and Objectives Narrative - Phase 2
Route Options Maps
Span Length & Pole Height
Pole Types
Pole Finish
Corridor Pole Configuration Examples
PSE Energize Eastside Community Outreach Summary - April 2016
Other PSE Alternatives Background Documents
Reference Maps
Proposed Transmission Line Segment Options Map
Corrosion Report
Letter to PSE from Olympic Pipeline Company Regarding Corrosion Report - December 2016
DNV-GL Corrosion Report - December 2016
DNV-GL No Action Alternative AC Interaction Graphs - April 2017
DNV-GL No Action Alternative AC Interaction Summary - April 2017
EMF Report
Power Engineers EMF Report Addendum - March, 2017
Power Engineers EMF Report, Revised - March, 2017
Photo Simulations
Views and Visual Index Map
Visual Simulations
Note: This is a large file and may take a few moments to download.
Photo Simulation North 3 - July 2017
Photo Simulation North 3 - March 2016
Photo Simulation North 14 - Corten - August 2017
Photo Simulation North 14 - Galvanized - August 2017
Photo Simulation North 14 - March 2016
Photo Simulation North 15 - August 2017
Photo Simulation North 16 - August 2017
Photo Simulation Segment J (South 24) - April 2016
Photo Simulation Segment J (South 25) - April 2016
Photo Simulation Segment J (Central 18) - May 2014
Photo Simulation Segment P (South 26) - April 2016
Photo Simulation Segment P (South 27) - April 2016
Photo Simulation Central 3 - July 2017
Photo Simulation Central 3 - May 2016
Photo Simulation Central 4 - August 2017
Photo Simulation Central 4 - May 2016
Photo Simulation Central 5 - September 2017
Photo Simulation Central 5 - August 2017
Photo Simulation Central 5 - May 2016
Photo Simulation Central 13 - August 2016
Photo Simulation Central 15 - Corten - July 2017
Photo Simulation Central 15 - Galvanized - July 2017
Photo Simulation Central 15 - May 2016
Photo Simulation Central 18 - Corten - July 2017
Photo Simulation Central 18 - Galvanized - July 2017
Photo Simulation Central 20 - August 2017
Photo Simulation Central 20 - May 2016
Photo Simulation Central 21 - August 2017
Photo Simulation Central 21 - May 2016
Photo Simulation Central 22 - August 2017
Photo Simulation Central 22 - May 2016
Photo Simulation Central 23 - August 2016
Photo Simulation Central 24 - August 2016
Photo Simulation Central 25 - August 2016
Photo Simulation Central 26 - August 2016
Photo Simulation Central 27 - August 2016
Photo Simulation Central 28 - August 2017
Photo Simulation Central 28 - August 2016
Photo Simulation Central 29 - September 2016
Photo Simulation Central 30 - Corten - July 2017
Photo Simulation Central 30 - Galvanized - July 2017
Photo Simulation Central 30 - September 2016
Photo Simulation Central 30 Willow 1 Segment 2- November 2016
Photo Simulation Central 31 - August 2017
Photo Simulation Central 31 - November 2016
Updated Photo Simulation Central 32 - September 2016
Photo Simulation Central 33 - October 2016
Photo Simulation Central 34 - October 2016
Photo Simulation Central 35 - October 2016
Photo Simulation Central 36 - November 2016
Photo Simulation Central 37 - August 2017
Photo Simulation Central 38 - August 2017
Photo Simulation Central 38 - January 2017
Photo Simulation Central 39 - August 2017
Photo Simulation Central 40 - August 2017
Photo Simulation South 12 - August 2017
Photo Simulation South 12 - July 2017
Photo Simulation South 12 - March 2016
Photo Simulation South 19 (C2AB) - July 2017
Photo Simulation South 19 (C16) - July 2017
Photo Simulation South 19 - Updated January 2017
Photo Simulation South 20 (C2) - July 2017
Photo Simulation South 20 (C16) - July 2017
Photo Simulation South 20 - Updated January 2017
Photo Simulation South 21 (C2) - July 2017
Photo Simulation South 21 (C16) - July 2017
Photo Simulation South 21 - Updated January 2017
Photo Simulation South 23 - Corten - July 2017
Photo Simulation South 23 - Galvanized - July 2017
Photo Simulation South 23 - August 2016
Photo Simulation South 24 (G) - Galvanized - July 2017
Photo Simulation South 24 - with Cell Equipment - November 2017
Photo Simulation South 24 - July 2017
Photo Simulation South 24 W (C1) - July 2017
Photo Simulation South 24 W - September 2016
Photo Simulation South 25 (C2AB) - Galvanized - July 2017
Photo Simulation South 25 (C2AB) - July 2017
Photo Simulation South 25 (C1) - July 2017
Photo Simulation South 25 (C16) - Corten - July 2017
Photo Simulation South 25 (C16) - Galvanized- July 2017
Photo Simulation South 25 - Updated September 2016
Photo Simulation South 26 (C2) - Corten - July 2017
Photo Simulation South 26 (C2) - Galvanized - July 2017
Photo Simulation South 26 (C16) - Corten - July 2017
Photo Simulation South 26 (C16) - Galvanized - July 2017
Photo Simulation South 26 - January 2017
Photo Simulation South 27 (C2) - July 2017
Photo Simulation South 27 (C16) - July 2017
Photo Simulation South 27 - January 2017
Photo Simulation South 28 - April 2016
Photo Simulation South 29 - April 2016
Photo Simulation South 30 - April 2016
Photo Simulation South 31 - April 2016
Photo Simulation South 34 - June 2016
Photo Simulation Richards Creek Substation - August 2017
Photo Simulation Richards Creek Substation - January 2017
Cultural Resource Reports
Cultural Alternatives Analysis - Redacted Version - June 2016
Geotechnical Reports
Energize Eastside Project Revised Targeted Critical Areas Geologic Hazard Evaluation - Newcastle
Energize Eastside Project Revised Targeted Critical Areas Geologic Hazard Evaluation - Bellevue
Energize Eastside Project Revised Targeted Critical Areas Geologic Hazard Evaluation - Renton
Energize Eastside Project Geologic Hazards Evaluation and Preliminary Geotechnical Engineering Services Report - December 2014
Energize Eastside Project Phase II Geotechnical Engineering Services Report - June 6, 2016
Energize Eastside Project Geotechnical Engineering Services Report - June 8, 2016
Critical Area Reports
Bellevue Energize Eastside Project Critical Areas Delineation Report - May 2016
Bypass Routes 1 & 2 Energize Eastside Critical Areas Addendum - July 2016
King County Energize Eastside Project Critical Areas Delineation Report - May 2016
Newcastle Energize Eastside Project Critical Areas Delineation Report - May 2016
Redmond Energize Eastside Project Critical Areas Delineation Report - May 2016
Renton Energize Eastside Project Critical Areas Delineation Report - May 2016
Segment O Critical Areas Addendum - April 2016
Segment P Critical Areas Addendum - May 2016
Vegetation Impact Analysis
Existing Corridor Vegetation Management Image - August 2016
PSE Veg Impact Analysis Summary Updated - September 2016
PSE Veg Impact Analysis Summary Richards Creek Updated - September 2016
PSE Vegetation Management Standards, 230kv Transmission Lines Updated - September 2016
Tree Inventory Reports
Bellevue Energize Eastside Project Tree Inventory Report - May 2016
Bypass Routes 1 & 2 Energize Eastside Project Tree Inventory Report - July 2016
King County Energize Eastside Project Tree Inventory Report - May 2016
Newcastle Energize Eastside Project Tree Inventory Report - May 2016
Redmond Energize Eastside Project Tree Inventory Report - May 2016
Renton Energize Eastside Project Tree Inventory Report - May 2016
Richards Creek Parcel Tree Inventory Report - July 2016
Segment O Energize Eastside Project Tree Inventory Report - May 2016
Segment P Energize Eastside Project Tree Inventory Report - May 2016
Methodology for Vegetation Impact Analysis
Substation
Richards Creek Substation Draft Grading and Fencing Plan - August 2016
Richards Creek Substation 230kv Preliminary Development Plan - March 2015
Richards Creek Substation Preliminary Grading and Fencing Plan - June 2016
Other Documents
Telecommunication Facilities Diagram
Energize Eastside Pole Structure Types - August 2017
Energize Eastside Roadway Alignment Transmission Configurations and Easement Requirements, 230kv Transmission Lines - June 2016
Energize Eastside Photo Simulation Methodology - June 2016
General Construction and Access Description - August 2016
Olympic Pipe Line Company Construction and Right of Way Requirements - March 2016
 
Phase 1 Materials
 
 
Phase 1 Draft EIS Comment Record
Note 1: This record includes emails, letters, meeting testimony and website comments received during the Phase 1 Draft EIS comment period. Due to its large size, it has been provided in two parts. They may take a few moments to download. To navigate the record and find a specific comment, we recommend downloading the files and using the bookmarks menus.
Note 2: The record was updated on May 17, 2016.
Part 1 - Phase 1 Draft EIS Comment Record
Part 2 - Phase 1 Draft EIS Comment Record
Phase 1 Draft EIS Public Hearing Summary
Hearings Summary
Phase 1 Draft EIS Document
Complete Phase 1 Draft EIS with Appendices
00 - Cover Letter, Fact Sheet, Table of Contents, Glossary
01 - Introduction and Summary
02 - Project Alternatives
03 - Earth
04 - Greenhouse Gas Emissions
05 - Water Resources
06 - Plants and Animals
07 - Energy and Natural Resources
08 - Environmental Health
09 - Noise
10 - Land Use and Housing
11 - Views and Visual Resources
12 - Recreation
13 - Historic and Cultural Resources
14 - Transportation
15 - Public Services
16 - Utilities
17 - References
18 - Distribution List
Appendix A - PSE Conservation Program
Appendix B - Potential Construction Equipment
Appendix C - Endangered and Threatened Species
Appendix D - Soil Types and Groundwater in Study Areas
Appendix E - Planning Documents Referenced for this Analysis
Appendix F - Potentially Applicable Comprehensive Plan and Shoreline Master Program Goals and Policies
Appendix G - Applicable Policies and Code Requirements for Views and Visual Resources
Appendix H - Historic and Cultural Sites
Appendix I - Registered Historic Properties
Appendix J - Description of Applicable Historic Registers
Appendix K - Interview Questions for Fire Departments
Appendix L - Interview Questions for Police Departments
Appendix M - Pipeline Safety Requirements and Plans Relating to Petroleum Pipelines
Interactive Maps
Nine maps in the Phase 1 Draft EIS have been converted to an online, interactive format to allow people to zoom in and out. Click on the below links to explore the maps.
Figure 3-1: Landslide and Erosion Hazard Areas
Figure 5-1: Major Water Resources
Figure 6-2: Vegetation Cover
Figure 10-2: Future Land Uses
Figure 10-5: Existing Land Uses
Figure 11-13: Property View Scores
Figure 12-1: Recreation Sites
Figure 16-1: Existing Electric Transmission and Natural Gas/Petroleum Pipelines
Figure 16-2: Existing Regional Wastewater and Water Lines
Hearing Exhibits
Exhibit boards were on display at the public hearings held during the Phase 1 Draft EIS comment period. Click on the below link to view the exhibits.
Hearing Exhibits - Phase 1 Draft EIS
Note 1: This record includes emails, letters, meeting testimony and website comments received during the Phase 1 Draft EIS comment period. Due to its large size, it has been provided in two parts. They may take a few moments to download. To navigate the record and find a specific comment, we recommend downloading the files and using the bookmarks menus.
Note 2: The record was updated on May 17, 2016.
Part 1 - Phase 1 Draft EIS Comment Record
Part 2 - Phase 1 Draft EIS Comment Record
Phase 1 Draft EIS Public Hearing Summary
Hearings Summary
Phase 1 Draft EIS Document
Complete Phase 1 Draft EIS with Appendices
00 - Cover Letter, Fact Sheet, Table of Contents, Glossary
01 - Introduction and Summary
02 - Project Alternatives
03 - Earth
04 - Greenhouse Gas Emissions
05 - Water Resources
06 - Plants and Animals
07 - Energy and Natural Resources
08 - Environmental Health
09 - Noise
10 - Land Use and Housing
11 - Views and Visual Resources
12 - Recreation
13 - Historic and Cultural Resources
14 - Transportation
15 - Public Services
16 - Utilities
17 - References
18 - Distribution List
Appendix A - PSE Conservation Program
Appendix B - Potential Construction Equipment
Appendix C - Endangered and Threatened Species
Appendix D - Soil Types and Groundwater in Study Areas
Appendix E - Planning Documents Referenced for this Analysis
Appendix F - Potentially Applicable Comprehensive Plan and Shoreline Master Program Goals and Policies
Appendix G - Applicable Policies and Code Requirements for Views and Visual Resources
Appendix H - Historic and Cultural Sites
Appendix I - Registered Historic Properties
Appendix J - Description of Applicable Historic Registers
Appendix K - Interview Questions for Fire Departments
Appendix L - Interview Questions for Police Departments
Appendix M - Pipeline Safety Requirements and Plans Relating to Petroleum Pipelines
Interactive Maps
Nine maps in the Phase 1 Draft EIS have been converted to an online, interactive format to allow people to zoom in and out. Click on the below links to explore the maps.
Figure 3-1: Landslide and Erosion Hazard Areas
Figure 5-1: Major Water Resources
Figure 6-2: Vegetation Cover
Figure 10-2: Future Land Uses
Figure 10-5: Existing Land Uses
Figure 11-13: Property View Scores
Figure 12-1: Recreation Sites
Figure 16-1: Existing Electric Transmission and Natural Gas/Petroleum Pipelines
Figure 16-2: Existing Regional Wastewater and Water Lines
Hearing Exhibits
Exhibit boards were on display at the public hearings held during the Phase 1 Draft EIS comment period. Click on the below link to view the exhibits.
Hearing Exhibits - Phase 1 Draft EIS
 
Scoping Documents
Phase 1 Draft EIS Scoping Report
Note: This report includes a summary of scoping meetings, meeting and notification materials, summary of scoping comments and final alternatives. This is a large file and may take a few moments to download.
Phase 1 Draft EIS Scoping Report
Note: This report includes a summary of scoping meetings, meeting and notification materials, summary of scoping comments and final alternatives. This is a large file and may take a few moments to download.
Phase 1 Draft EIS Scoping Comment Record Report - Revised Version
Note 1: This report includes emails, letters, meeting testimony and website comments received during the scoping period. To navigate the report and find a specific comment, we recommend downloading the file and using the bookmarks menu. This is a large file and may take a few moments to download.
Note 2: This report has been revised since it was first posted in July 2015 to include emails and letters submitted during the Phase 1 Draft EIS Scoping Comment period that were accidentally excluded from the report. To view the emails and letters that have now been included, navigate to the bookmark titled “Emails and Letters added November 2015.”
Meeting Testimony
Note 1: This report includes emails, letters, meeting testimony and website comments received during the scoping period. To navigate the report and find a specific comment, we recommend downloading the file and using the bookmarks menu. This is a large file and may take a few moments to download.
Note 2: This report has been revised since it was first posted in July 2015 to include emails and letters submitted during the Phase 1 Draft EIS Scoping Comment period that were accidentally excluded from the report. To view the emails and letters that have now been included, navigate to the bookmark titled “Emails and Letters added November 2015.”
Meeting Testimony
Bellevue Scoping Meeting Testimony
Kirkland Scoping Meeting Testimony
Newcastle Scoping Meeting Testimony
North Bellevue Scoping Meeting Testimony
Renton Scoping Meeting Testimony
Other Scoping Documents
Kirkland Scoping Meeting Testimony
Newcastle Scoping Meeting Testimony
North Bellevue Scoping Meeting Testimony
Renton Scoping Meeting Testimony
Other Scoping Documents
Background Documents - Project Need
Supplemental Eastside Solution Study Report - Redacted Version - May 2015
Independent Technical Analysis of Energize Eastside - April 2015
Supplemental Eastside Needs Assessment Report - Redacted Version - April 2015
Eastside Transmission Solutions Report – Redacted Version - February 2014
Eastside Needs Assessment Report – Redacted Draft - October 2013
Electrical Reliability Study Phase 2 Report - February 2012
 
Background Documents - PSE Energize Eastside Reports
Community Advisory Group Final Report
The purpose of this report is to document the work and summarize the recommendations of the Community Advisory Group convened by PSE to explore community preferences, priorities and concerns and to assess segments that could be combined to form a final route for the Energize Eastside 230kV transmission lines.
Community Advisory Group Final Report
The purpose of this report is to document the work and summarize the recommendations of the Community Advisory Group convened by PSE to explore community preferences, priorities and concerns and to assess segments that could be combined to form a final route for the Energize Eastside 230kV transmission lines.
Project Map
Map showing multiple 230kV corridors, transformation sites, and power plant sites considered.
Map showing multiple 230kV corridors, transformation sites, and power plant sites considered.
Eastside Needs Assessment Report Executive Summary
Executive summary of the “Eastside Needs Assessment” by the Quanta Technology engineering firm. This independent needs assessment reviewed population trends, electric load growth, economic development patterns, conservation programs, energy efficiency improvements, and other key trends. Studies demonstrated that different parts of the transmission system will not meet mandatory reliability requirements. The studies indicated that transmission lines will overload or are close to overloading starting in 2017.
Executive summary of the “Eastside Needs Assessment” by the Quanta Technology engineering firm. This independent needs assessment reviewed population trends, electric load growth, economic development patterns, conservation programs, energy efficiency improvements, and other key trends. Studies demonstrated that different parts of the transmission system will not meet mandatory reliability requirements. The studies indicated that transmission lines will overload or are close to overloading starting in 2017.
Energize Eastside PSE Screening Study
Energy and Environmental Economics (E3) was retained to provide a screening-level assessment of the potential for non-wires alternatives to defer the proposed upgrades on the Eastside portion of Puget Sound Energy’s (PSE) transmission system. E3’s analysis indicates that the cost-effective non-wires potential in the area, including energy efficiency (EE), demand response (DR) and distributed generation (DG) measures, does not represent a permanent alternative to avoid the need for the transmission upgrade options. This assessment also indicates that the non-wires potential alone is not sufficient to cost-effectively defer the need date of transmission upgrades while maintaining equivalent reliability levels.
Energy and Environmental Economics (E3) was retained to provide a screening-level assessment of the potential for non-wires alternatives to defer the proposed upgrades on the Eastside portion of Puget Sound Energy’s (PSE) transmission system. E3’s analysis indicates that the cost-effective non-wires potential in the area, including energy efficiency (EE), demand response (DR) and distributed generation (DG) measures, does not represent a permanent alternative to avoid the need for the transmission upgrade options. This assessment also indicates that the non-wires potential alone is not sufficient to cost-effectively defer the need date of transmission upgrades while maintaining equivalent reliability levels.
Eastside Solution Study Executive Summary
The planning analysis discussed in this report has identified five alternative solutions to address the transmission capacity deficiency identified in the “Eastside Needs Assessment Report – Transmission System King County” dated October 2013 (“Needs Assessment Report”). Each of these five solutions fully satisfies the needs identified in the Needs Assessment Report and satisfies the solution longevity and constructability requirements established by PSE as discussed in the body of this report.
The planning analysis discussed in this report has identified five alternative solutions to address the transmission capacity deficiency identified in the “Eastside Needs Assessment Report – Transmission System King County” dated October 2013 (“Needs Assessment Report”). Each of these five solutions fully satisfies the needs identified in the Needs Assessment Report and satisfies the solution longevity and constructability requirements established by PSE as discussed in the body of this report.
Energize Eastside Narrative and Probable Significant Impacts
Describes the system planning context, proposal development, proposal narrative, demand side reduction/non-wire technologies, probable significant environmental impacts, and the no action alternative.
Describes the system planning context, proposal development, proposal narrative, demand side reduction/non-wire technologies, probable significant environmental impacts, and the no action alternative.
PSE 2013 Integrated Resource Plan
This Integrated Resource Plan presents a long-term forecast of the lowest reasonable cost combination of resources necessary to meet the needs of Puget Sound Energy’s customers over the next 20 years. The plan presented here will change as circumstances change, and actual resource acquisitions will take place in the real – rather than the hypothetical – marketplace. But, examining the long-term implications of PSE customers' energy needs every two years makes it possible to identify many challenges as they appear on the horizon, study them as they approach, and better prepare to meet them.
This Integrated Resource Plan presents a long-term forecast of the lowest reasonable cost combination of resources necessary to meet the needs of Puget Sound Energy’s customers over the next 20 years. The plan presented here will change as circumstances change, and actual resource acquisitions will take place in the real – rather than the hypothetical – marketplace. But, examining the long-term implications of PSE customers' energy needs every two years makes it possible to identify many challenges as they appear on the horizon, study them as they approach, and better prepare to meet them.
Constraint and Opportunity Study for Linear Site Selection Executive Summary
PSE contracted with Tetra Tech, Inc. to employ a geographic information system (GIS)‐based Linear Routing Tool (LRT) to conduct a broad evaluation of possible transmission line routes. This is the executive summary prepared by PSE.
PSE contracted with Tetra Tech, Inc. to employ a geographic information system (GIS)‐based Linear Routing Tool (LRT) to conduct a broad evaluation of possible transmission line routes. This is the executive summary prepared by PSE.
Constraint and Opportunity Study for Linear Site Selection
PSE contracted with Tetra Tech, Inc. to employ a geographic information system (GIS)‐based Linear Routing Tool (LRT) to conduct a broad evaluation of possible transmission line routes.
PSE contracted with Tetra Tech, Inc. to employ a geographic information system (GIS)‐based Linear Routing Tool (LRT) to conduct a broad evaluation of possible transmission line routes.
Eastside 230 kV Project Underground Feasibility Study
This study focuses on replacing and upgrading the existing 115 kV overhead lines with an underground 230 kV system from an engineering and constructability standpoint. The study identifies three route alternatives with cost estimates and project schedules.
Study
Appendix A Part 1
Appendix A Part 2
Appendix B
This study focuses on replacing and upgrading the existing 115 kV overhead lines with an underground 230 kV system from an engineering and constructability standpoint. The study identifies three route alternatives with cost estimates and project schedules.
Study
Appendix A Part 1
Appendix A Part 2
Appendix B
 
Background Documents - Other
BPA Response to City of Bellevue Regarding NEPA Nexus
Eastside System Energy Storage Alternatives Screening Study - March, 2015
Energize Eastside EIS Public Involvement Plan - Updated March, 2016
Final Technical Memo on Power-Frequency Electric and Magnetic Fields - January, 2016
Interagency Agreement
IPR Comprehensive Assessment of Demand-Side Resource Potentials (2014-2033) - May, 2013
Lake Washington Submarine Cable Alternative Feasibility Study - June, 2015
Letter Clarifying Bonneville Power Administration role in Energize Eastside
Letter Clarifying Columbia Grid Role in Energize Eastside
PSE Emails Referenced in the Phase 1 Draft EIS
PSE Energize Eastside Economic Considerations Report - January, 2016
PSE Energize Eastside Outage Cost Study - October, 2015
PSE Response to EIS Questions - July 6, 2015
PSE - Additional Information Provided by PSE via Email
Memorandum of Agreement Between Bonneville Power Administration, Seattle City Light and Puget Sound Energy - January, 2012
Notice of Phase 1 Draft EIS and Public Hearings/Open Houses
Shepard Technical Memo - November, 2015
Stantec Review Memo on the Eastside Needs Assessment Report
BPA Response to City of Bellevue Regarding NEPA Nexus
Eastside System Energy Storage Alternatives Screening Study - March, 2015
Energize Eastside EIS Public Involvement Plan - Updated March, 2016
Final Technical Memo on Power-Frequency Electric and Magnetic Fields - January, 2016
Interagency Agreement
IPR Comprehensive Assessment of Demand-Side Resource Potentials (2014-2033) - May, 2013
Lake Washington Submarine Cable Alternative Feasibility Study - June, 2015
Letter Clarifying Bonneville Power Administration role in Energize Eastside
Letter Clarifying Columbia Grid Role in Energize Eastside
PSE Emails Referenced in the Phase 1 Draft EIS
PSE Energize Eastside Economic Considerations Report - January, 2016
PSE Energize Eastside Outage Cost Study - October, 2015
PSE Response to EIS Questions - July 6, 2015
PSE - Additional Information Provided by PSE via Email
Memorandum of Agreement Between Bonneville Power Administration, Seattle City Light and Puget Sound Energy - January, 2012
Notice of Phase 1 Draft EIS and Public Hearings/Open Houses
Shepard Technical Memo - November, 2015
Stantec Review Memo on the Eastside Needs Assessment Report
Application Materials Submitted by PSE to the City of Bellevue (File #14-139122-LE)
Energize Eastside Narrative of Probable Significant Impacts
Energize Eastside PSE Screening Study
Eastside Needs Assessment Report Executive Summary
Eastside Needs Assessment Report Redacted
Eastside Solution Study Executive Summary
Eastside Transmission Solutions Report Redacted
Project Map
Energize Eastside PSE Screening Study
Eastside Needs Assessment Report Executive Summary
Eastside Needs Assessment Report Redacted
Eastside Solution Study Executive Summary
Eastside Transmission Solutions Report Redacted
Project Map
 
Websites
Citizen’s Guide to SEPA Review and Commenting
www.ecy.wa.gov/programs/sea/sepa/citizensguide/citizensguide.htm
City of Bellevue Electrical Facilities Webpage
http://www.ci.bellevue.wa.us/electrical-facilities.htm
City of Bellevue Webpage with Link to Independent Technical Analysis of Energize Eastside
http://www.ci.bellevue.wa.us/electrical-facilities-council.htm
City Codes
http://www.codepublishing.com/wa/bellevue/
http://www.codepublishing.com/wa/kirkland/
http://www.codepublishing.com/WA/Newcastle/
http://www.codepublishing.com/WA/redmond/
http://www.codepublishing.com/wa/renton/
City Websites
http://www.ci.bellevue.wa.us/
http://www.kirklandwa.gov/
http://www.ci.newcastle.wa.us/
http://www.redmond.gov/
http://rentonwa.gov/
Puget Sound Energy Electric Tarriff G
http://pse.com/aboutpse/Rates/Documents/elec_sch_080.pdf
Puget Sound Energy's Energize Eastside Website
http://energizeeastside.com/
Washington State Department of Ecology's SEPA Webpage
http://www.ecy.wa.gov/programs/sea/sepa/e-review.html
Citizen’s Guide to SEPA Review and Commenting
www.ecy.wa.gov/programs/sea/sepa/citizensguide/citizensguide.htm
City of Bellevue Electrical Facilities Webpage
http://www.ci.bellevue.wa.us/electrical-facilities.htm
City of Bellevue Webpage with Link to Independent Technical Analysis of Energize Eastside
http://www.ci.bellevue.wa.us/electrical-facilities-council.htm
City Codes
http://www.codepublishing.com/wa/bellevue/
http://www.codepublishing.com/wa/kirkland/
http://www.codepublishing.com/WA/Newcastle/
http://www.codepublishing.com/WA/redmond/
http://www.codepublishing.com/wa/renton/
City Websites
http://www.ci.bellevue.wa.us/
http://www.kirklandwa.gov/
http://www.ci.newcastle.wa.us/
http://www.redmond.gov/
http://rentonwa.gov/
Puget Sound Energy Electric Tarriff G
http://pse.com/aboutpse/Rates/Documents/elec_sch_080.pdf
Puget Sound Energy's Energize Eastside Website
http://energizeeastside.com/
Washington State Department of Ecology's SEPA Webpage
http://www.ecy.wa.gov/programs/sea/sepa/e-review.html